Building first production hall completely closed.

The construction of the first production building, constructed for our customer ZF Slovakia, has progressed fast forward. We are pleased to see the outside construction, as well as the inside floor, have been completely finished, on time. Next stage is the implementation of all interior utilities, as well as finishing all office area

 

Work in Progress- 22.10.2018

The roof of the production hall for ZF Slovakia, a.s is currently under construction.

By the end of November 2018 the production hall for ZF Slovakia a.s will be wind and water proof.

The production hall of Punch Precision, s.r.o will be wind and water proof at the beginning of February 2019.
Pre-production in Punch Precision, s.r.o is planned for July 2019.

Foundation Stone Ceremony

The construction is planned to be ready for moving in throughout the first quartile of the year 2019 and is growing at a top notch speed.
In order to celebrate the mark of the start of the construction, Punch Precision Detva, s.r.o and ZF Slovakia, a.s have met at the industrial park Punch Campus Detva for the foundation stone ceremony on the 3.10.2018.
Both companies officials have taken their part in marking both foundation stones with hammers. The Mayor of Detva showed his support by being a part in the act as well.

Interviewed by Detva TV

Last week, Detva TV visit us in our pop-up office in Detva. We were happy to give some further info on the project and its timing.

Enjoy the video!

 

Construction work started!

In July 2018, Punch Property has started the first steps of the constructiowith the removal of soil.
During the stage of preparatory work, electrical connections for the building has been executed.

Stay tuned for next updates!